Table of Contents Introduction Overall Summary

Overall Assessment

Acknowledgements Download full report

Printer friendly version of the current pageOverall Project Assessment: Wet Woods Restoration Project - Final Technical Report
Compiled by Scottish Natural Heritage on behalf of Scottish Natural Heritage
Forest Enterprise, Forestry Commission, The Royal Society for the Protection of Birds and Highland Birchwoods: September 2002

4.1 Has the project achieved its objectives? Successes and failures

Reference to section 2.1.2 shows that the restoration targets for bog woodland were considerably exceeded (155.5% of target) for habitat restoration and only just fell short (98% of target) with regard to hydrological restoration. The general and site specific research projects produced much useful information that was of benefit during the Project and also adds to our knowledge and understanding of bog woodlands. These reports with wider implications will be available through the Wet Woods web site and the SNH web site: the Age Structure of Scots pine woodland has also been published in Scottish Forestry (Vol. 56 No. 3 2002, p135-243). All of this was achieved well within budget and therefore represents very good value for money.

The early indications are that bog woodland aspects of the Project have been particularly successful in spite of early complications. These illustrated the problems associated with developing programmes such as this. Parts of the areas that have been restored were very degraded and it was difficult to accurately assess before the work began what the situation would be on the ground with respect to its hydrological state. Also it was difficult to assess the ability of machines to carry out the work and for example Map 3.2.3.f shows how much of the work at Mondhuie had to be done manually, which is more expensive and time consuming than machine felling. More accurate preliminary mapping would have reduced the uncertainties and certainly the experience of this project, and the recent improvement in digital mapping techniques, will mean that any future work will be based on a more accurate understanding of the problem. However if, as was the case in parts of the site, the timber was of very poor growth form and had become intertwined and was therefore very difficult to harvest.

Learning from experience and interaction with others was an integral part of the Project. As can be seen from Section 3.3 there was considerable interaction with various groups visiting the sites and the Project Manager and other staff associated with the Project visiting other sites and Projects. The Conference, which was attended by over 100 delegates, provided an excellent forum for interchange of ideas and the presence of speakers from Sweden and Finland gave a valuable insight into the Scandinavian experience. It was particularly heartening to get positive feedback from the Finnish delegate as they have considerably more experience of bog woodland management in their country.

The work on the Conon met the original target and following permission to extend the Project a considerable additional area was restored. Unfortunately delays in getting formal agreement to extend the Project meant that the additional work planned for the Lower Spey Bay did not occur during the required period as management considerations meant that the work had to be undertaken when ground conditions are suitable. Although this had an impact on total Project outputs that part of the site is in the ownership of Forest Enterprise and therefore its continued future positive management is ensured.

Work on the Conon Strategy has perhaps been one of the more difficult tasks. The successful implementation of strategies depends on the willingness of interested parties to sign up to them and this in turn depends on a number of other issues. It was therefore felt that rather than try and produce something that was agreed by all parties, and consequently likely to be quite limited in scope, it would be more useful to provide a framework document that could be used to guide and encourage local initiatives. It is now proposed that a full consultation process will commence in 2003 with a view to have having a management forum in place by 2004. Obviously this will depend on the co-operation of partners but as can be seen below informal discussions about the strategy are already paying dividends.

4.2 Conservation benefits

The most obvious benefit is the area that has been restored. Although for bog woodland habitat and hydrological restoration have been measured separately they are of course closely linked and it would not be possible or sensible to achieve one without doing the other. As can be seen the work on some of the sites, e.g. Mondhuie (Map 3.2.3.a) and North Abernethy (Map 3.2.4.b), has built on work that has been undertaken before the Project began but the Project has been instrumental in ensuring that the work has been completed and in a much shorter timescale that would have been possible otherwise. In other sites, e.g. Inshriach, the Project has been the catalyst for the work being undertaken. As a result there are now no major areas within the sites that have been worked that will require further significant areas of work. All will be monitored as part of SNH's SCM programme and some will be subject to more specific local monitoring to measure success and progress and to also see if any remedial work is required and to measure the success of that.

As a result of the Project an additional 214.3 ha of bog woodland habitat was submitted to the EC as additions to the Monadh Mor and Cairngorm cSAC on 29 January 2001.

Although the area associated with the restoration of the Conon is considerably less it has nevertheless been significant and considerably more than originally planned. The problems associated with the Conon are more or less restricted to the presence of exotic species as the component parts of the cSAC are located on areas close to the River Conon where the hydrological regime is less altered than areas back from the river. The presence of exotics within the rest of the catchment will mean that there is a continuing need to monitor the site and take remedial action as necessary. However because of the major work that has been achieved by the Project the need for further work will be considerably reduced. Unlike the bog woodland sites all of the River Conon is in private ownership. However as with other sites it will be monitored as part of SNH's SCM programme and financial aid for management will be available through national programmes such as the Scottish Forestry Grants Scheme, the Rural Stewardship Scheme and SNH's own developing Natural Care Programme which is looking at targeting top up funding to designated sites and Natura sites in particular. The developing Conon strategy already appears to be paying dividends. The work that has been undertaken has raised the profile of the conservation issues and resulted in new proposals being brought forward. The suggested restoration of residual alluvial woodland and the development of a new salmon spawning redd along the old river channel on Dunglass Island is the direct result of discussions about the Conon Strategy. An approach from a land manager about the control of Himalayan Balsam on the lower Conon has also been inspired by the work undertaken as part of the Project to deal with rhododendron and Physocarpus. Both these possible future projects show a desire to become involved in partnership working to produce results on the ground.


4.3 Incentive/pump-priming effects and networking

The Project has built on working relations that have developed over a number of years of involvement with LIFE Projects under the umbrella of the Caledonian Partnership. This meant that there were already good working relationships between the partners and the current Project has added to this. This close liaison will be invaluable as other LIFE Projects, such as the Capercaillie Project, and other joint working opportunities arise.

During the Project the Project Manager and a number of key personnel associated with the Project took advantage of opportunities to visit other projects and participate in Green Week. This all adds to the networking opportunities and there have been a number of corresponding visits from a divers range of interested parties. Overall these exchanges have had a significant role in developing contacts and raising interest and awareness that will prove to be useful in the future.

The pump-priming aspect of the Project has been of great importance in promoting the management of Wet Wood habitats. Bog woodlands by there very nature have little inherent socio-economic benefits, apart from the perceived gains associated with agricultural or silvicultural improvement, and are therefore often overlooked. The Project has raised the awareness of the need to manage these areas and has demonstrated that this can be done with the careful application of management techniques that are available. Similarly the impact on the consideration given to the management of alluvial woodlands will be of significant benefit as the experience gained is disseminated.

4.4 Demonstration and benefits of EU funding

Although the partners have some years of experience of managing bog woodlands this Project allowed the lessons learnt and experience gained from elsewhere to be put to use at a scale that was not previously thought to be achievable. This was a direct result of the opportunity to make use of money available under the LIFE Nature programme to undertake proactive work on candidate Special Areas of Conservation. This availability of funds is seen as a very important catalyst in ensuring that work is undertaken and that full advantage is made of the opportunities for networking and dissemination. It is therefore hoped that not only will the sites directly managed benefit from the work undertaken but others will also benefit as a result of the ethos of partnership working that these projects engender and that dissemination of the results will encourage land managers elsewhere.

4.5 Socio-economic effects

The main measurable socio-economic benefit that this Project has brought has been the work that has been carried out by local contractors. All of the Project locations can be considered to be economically vulnerable where opportunities for rural employment are often at a premium. Although much of the work is one off the Project has provided opportunities for local contractors during this period. The nature of the work has often meant that it is labour intensive as shown by the need to hand fell 63 hectares at Mondhuie. Similarly the novel nature of the work has allowed local contractors to develop new skills which will prove to be useful as they seek new contracts. It also benefits the sites directly as there is now an experienced group of contractors who are used the different requirements of conservation, as opposed to economically, lead management.

4.6 The future: prolonging the effects of the project/further action needed

As has been stated in the main body of the report approximately 95% of the Project area lies within land owned by Forest Enterprise, Scottish Natural Heritage or the RSPB and therefore are covered by existing commitments to manage these areas for nature conservation in the long term. All of the other areas are also underpinned by domestic legislation as they are parts of larger Sites of Special Scientific Interest and therefore will be afforded the protection provided by this designation. All of the sites will be monitored as part of SNH's Site Condition Monitoring programme and some e.g. Mondhuie will be subject to more intensive surveying as outlined above. Although at his stage there are not thought to be any outstanding issues it is felt that there are sufficient systems in place to ensure that any work that is identified as a result of monitoring will be undertaken.

The development of sustainable management for the residual alluvial woodland of the Conon is likely to take several years. The dissemination of SNH’s Conon Strategy to the other stakeholders and the possible formation of a management group over the next two years is the start of the process. The move from merely preventing deterioration of the cSAC habitats to their enhancement and expansion will take several woodland cycles.

The management of alien exotics is also a long-term project. Due to their invasive nature some species may need control over several years or may re-invade following initial eradication. The control of these species will therefore have to continue for several years beyond the life of the project and will need the support of public funding in the form of SFGS, grants and agri-environment schemes.